I wrote some stuff about my recent experiences...
https://wiki.diyfaq.org.uk/index.php?title=External_wall_insulation,_a_case_study
Probably still needs a bit of tweaking, so let me know if you spot
anything that does not make sense, or is missing.
On 30/06/2026 16:27, John Rumm wrote:
I wrote some stuff about my recent experiences...
https://wiki.diyfaq.org.uk/index.php?
title=External_wall_insulation,_a_case_study
Probably still needs a bit of tweaking, so let me know if you spot
anything that does not make sense, or is missing.
Wow! What a cracking job John. Glad I didn't have to do that - it would probably have killed me.
Thank you.
I wrote some stuff about my recent experiences...
https://wiki.diyfaq.org.uk/index.php?title=External_wall_insulation,_a_case_study
Probably still needs a bit of tweaking, so let me know if you spot
anything that does not make sense, or is missing.
On 30 Jun 2026 at 16:27:12 BST, John Rumm wrote:
I wrote some stuff about my recent experiences...
https://wiki.diyfaq.org.uk/index.php?title=External_wall_insulation,_a_case_study
Probably still needs a bit of tweaking, so let me know if you spot
anything that does not make sense, or is missing.
Looks superb, well done. I'll have a proper read later. Initial Qs:
* How much did it/would it cost - say, overall and per m2? -u30k overall, if labour is -u400/day? A.I. reckons -u100 - -u200 m2.
Scaffolding is a big chunk of
the cost - maybe -u1000/week for wrap-around scaffold in your case? Almost worth buying?!
* I can't see (from a quick read) how the ground level/below DPC detailing was
achieved. Did you go below ground/switch to XPS for example? Or accept a bit of compromise insulation wise at ground level?
* I'm having a bit of an ongoing argument/discussion with a planner friend about planning permission/regs compliance - he seems to think that such work is not within permitted development. I think it is - obviously assuming no conservation and listed type considerations.
Also building regs - did that
significantly inform your design decisions? I'd assume you self-certify? TBH I'm still confused about the whole regs and retrofit compliance side of things, how regs 'equal' PAS 2030 etc. . . . (!)
On 01/07/2026 09:28, wasbit wrote:
On 30/06/2026 16:27, John Rumm wrote:
I wrote some stuff about my recent experiences...
https://wiki.diyfaq.org.uk/index.php?
title=External_wall_insulation,_a_case_study
Probably still needs a bit of tweaking, so let me know if you spot
anything that does not make sense, or is missing.
Wow! What a cracking job John. Glad I didn't have to do that - it
would probably have killed me.
Thank you.
Yeah, well it seemed simple enough in concept... but turned out to be
quite a endurance marathon in the end!
I have clad farm buildings with feather edge treated timber over rigid
foam using *lost tite* screws. Basically a woodscrew with a long plain
shank but having retaining rings near the head.
Mostly screwed into timber building frame but also works for brick/block.
With the insulation and first board temporarily located, drill through
from the outside using a suitable masonry or conventional drill. Start a fixing plug to the screw and tap into the hole. Use drill driver to seat home and move on to the next fixing. Once the board ends are secure, the whole row of new fixings can be drilled to save swapping drill bits.
I have no idea where this might fit in building regulations:-)>
On 01/07/2026 10:00, John Rumm wrote:
On 01/07/2026 09:28, wasbit wrote:
On 30/06/2026 16:27, John Rumm wrote:
I wrote some stuff about my recent experiences...
https://wiki.diyfaq.org.uk/index.php?
title=External_wall_insulation,_a_case_study
Probably still needs a bit of tweaking, so let me know if you spot
anything that does not make sense, or is missing.
Wow! What a cracking job John. Glad I didn't have to do that - it
would probably have killed me.
Thank you.
Yeah, well it seemed simple enough in concept... but turned out to be
quite a endurance marathon in the end!
I have clad farm buildings with feather edge treated timber over rigid
foam using *lost tite* screws. Basically a woodscrew with a long plain
shank but having retaining rings near the head.
Mostly screwed into timber building frame but also works for brick/block.
With the insulation and first board temporarily located, drill through
from the outside using a suitable masonry or conventional drill. Start a fixing plug to the screw and tap into the hole. Use drill driver to seat home and move on to the next fixing. Once the board ends are secure, the whole row of new fixings can be drilled to save swapping drill bits.
I wrote some stuff about my recent experiences...
https://wiki.diyfaq.org.uk/index.php? title=External_wall_insulation,_a_case_study
Probably still needs a bit of tweaking, so let me know if you spot
anything that does not make sense, or is missing.
On 30/06/2026 16:27, John Rumm wrote:
I wrote some stuff about my recent experiences...
https://wiki.diyfaq.org.uk/index.php?
title=External_wall_insulation,_a_case_study
Probably still needs a bit of tweaking, so let me know if you spot
anything that does not make sense, or is missing.
My neighbours clad their house. They used masses of rock wool, which is inherently non-combustible. Did you consider that, instead of PIR?
I appreciate that PIR, applied in the way you have, with a cement board cladding is not really a fire risk, and it's a low rise building, but ...
On 01/07/2026 10:49, RJH wrote:
On 30 Jun 2026 at 16:27:12 BST, John Rumm wrote:
I wrote some stuff about my recent experiences...
https://wiki.diyfaq.org.uk/index.php?title=External_wall_insulation,_a_case_study
Probably still needs a bit of tweaking, so let me know if you spot
anything that does not make sense, or is missing.
Looks superb, well done. I'll have a proper read later. Initial Qs:
* How much did it/would it cost - say, overall and per m2? -u30k overall, if >> labour is -u400/day? A.I. reckons -u100 - -u200 m2.
I have no idea what a commercial quote would be.
The insulation was -u1,250, and the main cladding order with most of the trims etc was about -u6,700. When you add in all the other stuff like
screws, sand cement, linear drain, timber battens, and a shed load of
tapes, sealants, glues etc and a skip or two then you are up to about -u10,300.
(I also bought some extra tools - but since I get to keep them, I don't include them in the cost unless they are "consumables" (blades, discs etc))
Scaffolding is a big chunk of
the cost - maybe -u1000/week for wrap-around scaffold in your case? Almost >> worth buying?!
The scaffolding cost -u936 and I kept it for about 4 weeks. So perhaps
half as much again if also doing the back. I bought some ordinary
building trestles for the easy side - those were about -u145 inc
delivery. An extra 4 might have been worth it - but the layout of the
planks enforced by the windows made it easy enough to do in sections
without needing to move the access kit too much.
* I can't see (from a quick read) how the ground level/below DPC detailing was
achieved. Did you go below ground/switch to XPS for example? Or accept a bit >> of compromise insulation wise at ground level?
Thus far I have not changed anything below interior floor level. The underfloor volume is vented (air bricks etc) so I is questionable if
there is much additional value to insulating the "skirts" at the side.
* I'm having a bit of an ongoing argument/discussion with a planner friend >> about planning permission/regs compliance - he seems to think that such work >> is not within permitted development. I think it is - obviously assuming no >> conservation and listed type considerations.
I did a bit of research on whether changes to the visual appearance were
of consequence. From what I could find, the answer was no, unless in a conservation area. (also the change in appearance is in keeping with the local architectural style, and does not affect the road facing elevation anyway)
Also building regs - did that
significantly inform your design decisions? I'd assume you self-certify? TBH >> I'm still confused about the whole regs and retrofit compliance side of
things, how regs 'equal' PAS 2030 etc. . . . (!)
I don't have an answer for the more general question...
On 1 Jul 2026 at 12:39:06 BST, John Rumm wrote:
On 01/07/2026 10:49, RJH wrote:
-u400 per person/day, at a guess.* How much did it/would it cost - say, overall and per m2? -u30k overall, if
labour is -u400/day? A.I. reckons -u100 - -u200 m2.
I have no idea what a commercial quote would be.
The insulation was -u1,250, and the main cladding order with most of the
trims etc was about -u6,700. When you add in all the other stuff like
screws, sand cement, linear drain, timber battens, and a shed load of
tapes, sealants, glues etc and a skip or two then you are up to about
-u10,300.
Interesting, thanks.
Scaffolding is a big chunk of
the cost - maybe -u1000/week for wrap-around scaffold in your case? Almost >>> worth buying?!
The scaffolding cost -u936 and I kept it for about 4 weeks. So perhaps
half as much again if also doing the back. I bought some ordinary
building trestles for the easy side - those were about -u145 inc
delivery. An extra 4 might have been worth it - but the layout of the
planks enforced by the windows made it easy enough to do in sections
without needing to move the access kit too much.
Trestles would safely see to over half the height, saving a fair chunk of the scaffold hire. If storing the trestles (or selling them) isn't a problem, a good investment.
I did a bit of research on whether changes to the visual appearance were
of consequence. From what I could find, the answer was no, unless in a
conservation area. (also the change in appearance is in keeping with the
local architectural style, and does not affect the road facing elevation
anyway)
Also building regs - did that
significantly inform your design decisions? I'd assume you self-certify? TBH
I'm still confused about the whole regs and retrofit compliance side of
things, how regs 'equal' PAS 2030 etc. . . . (!)
I don't have an answer for the more general question...
It was more how PAS/regs/certification etc informed your project. Looks 'right' to me . . .
| Sysop: | Amessyroom |
|---|---|
| Location: | Fayetteville, NC |
| Users: | 70 |
| Nodes: | 6 (0 / 6) |
| Uptime: | 01:54:49 |
| Calls: | 949 |
| Calls today: | 1 |
| Files: | 1,325 |
| Messages: | 281,112 |